Fast Track Arbitration in Construction Disputes

By: Qarrar Somji

Date: 08/05/2026

International arbitration remains the preferred dispute resolution mechanism for many major construction and infrastructure projects. However, construction businesses have criticised arbitration for becoming slower, more document-heavy, and increasingly expensive.

Fast track arbitration, sometimes referred to as expedited arbitration, is intended to address that problem. Institutional rules such as the ICC expedited procedure are designed to shorten timelines, limit procedural complexity, and give tribunals stronger tools to dispose of weak claims early. Recent reforms under the Arbitration Act 2025 are also expected to strengthen confidence in summary disposal for London-seated arbitrations.

If you are working on international or high-value domestic projects, these changes may create opportunities to resolve narrower construction disputes more quickly and with greater procedural certainty.

Summary

  1. Why Construction Claims Drag On
  2. What is Fast Track Arbitration in a Construction Context?
  3. Strategic Use Cases
  4. Summary Determination: Cutting Through Meritless Claims
  5. Fast Track Awards and the Arbitration Act 2025

The Traditional Bottleneck: Why Construction Claims Drag On

Construction disputes are often document-heavy and technically complex. Even narrow claims may involve expert evidence, extensive disclosure exercises, and multiple parties.

That complexity has historically made some practitioners cautious about expedited arbitration procedures. A dispute over delay, design responsibility, or payment entitlement can quickly expand into lengthy procedural arguments before the substantive issues are fully addressed.

Fast track arbitration does not remove complexity entirely. However, it changes how the tribunal manages the process. The aim is to narrow issues earlier, reduce procedural excess, and prevent parties from using delay tactically.

What is Fast Track Arbitration in a Construction Context?

Fast track arbitration refers to procedural rules designed to produce an arbitral award more quickly and with reduced procedural formality. Under the ICC expedited procedure, tribunals are given greater case management powers to shorten timelines and streamline the arbitration process.

The ICC expedited procedure currently applies automatically to arbitration agreements concluded after 1 January 2021 where the amount in dispute does not exceed US$3 million, unless the parties opt out. Parties may also agree to use the expedited procedure voluntarily for higher-value disputes.

The process typically involves:

  • compressed procedural timetables
  • restrictions on document production
  • shorter written submissions
  • reduced or limited oral hearings
  • the possibility of a sole arbitrator instead of a three-member tribunal

The tribunal may also decide the dispute on documents alone where appropriate.

This reflects a broader shift in international arbitration practice. The 2025 Queen Mary University of London and White & Case International Arbitration Survey reported that 42% of arbitration users had used expedited or simplified arbitration procedures in the previous five years. Of those, 84% had found them more efficient than non-expedited processes and 76% would use them again.

In a construction context, expedited arbitration is generally most effective where the dispute is legally or technically narrow, even if the underlying project itself is large. Examples may include:

  • interpretation of a contractual liability cap
  • payment disputes tied to certification
  • discrete variation valuation issues
  • jurisdiction disputes
  • guarantee or bond enforcement disputes

This differs significantly from statutory adjudication under the Housing Grants, Construction and Regeneration Act 1996. Statutory adjudication is a mandatory statutory process for many UK construction contracts and is intended to maintain cash flow during projects through temporarily binding decisions.

Fast track arbitration is different. It remains a consensual dispute resolution mechanism governed by the parties’ arbitration agreement and institutional rules. Awards are final and binding, subject to limited challenge rights.

Strategic Use Cases: Minimising Disruption on Ongoing Projects

Fast track arbitration is most effective where parties need a binding decision quickly to avoid disrupting an ongoing project.

This issue frequently arises on international projects where statutory adjudication rights do not exist, or where the governing contract deliberately excludes adjudication mechanisms in favour of arbitration.

In practice, expedited arbitration may help:

  • unlock stalled payment disputes
  • resolve narrow contractual interpretation issues
  • determine interim responsibility for delay events
  • address disputes affecting project continuation
  • avoid escalation into broader multi-party proceedings

For example, a contractor and employer may fundamentally disagree about whether a particular exclusion clause prevents recovery for prolongation costs. If that issue can be resolved early through expedited arbitration or summary disposal, it may avoid months of wider evidential disputes that ultimately depend on the same contractual point. This can be commercially important on live projects where uncertainty itself becomes disruptive.

Summary Determination: Cutting Through Meritless Claims

Summary determination, sometimes called summary disposal, allows an arbitral tribunal to dismiss claims or defences that have no real prospect of success without requiring a full evidential hearing.

Historically, some tribunals approached this cautiously because of concerns about due process and enforceability. That often meant weak claims still generated substantial disclosure, expert evidence, and hearing costs before eventually being rejected. That position has gradually changed as arbitral institutions and courts have become more supportive of robust procedural case management.

In construction disputes, summary determination may be appropriate where:

  • the dispute turns on a narrow contractual interpretation issue
  • limitation periods clearly bar the claim
  • the claim contradicts agreed contractual mechanisms
  • there is no realistic evidential basis for the defence advanced

For example, a contractor may seek damages that are expressly excluded under a negotiated limitation clause within the contract. If the wording is clear and the issue is purely one of contractual interpretation, a tribunal may determine the issue summarily rather than requiring a full merits hearing. This can substantially reduce both cost and disruption.

Fast Track Awards and the Arbitration Act 2025

One of the most significant recent developments for London-seated arbitration is the Arbitration Act 2025.

The Act expressly confirms that tribunals may issue summary awards where a claim, defence, or issue has no real prospect of succeeding. This brings the position in arbitration closer to the summary judgment framework already familiar in court litigation. The reform matters because it provides clearer statutory support for decisive procedural management.

Previously, there were concerns that the aggressive use of summary disposal might create enforcement risks or allegations of procedural unfairness. The Arbitration Act 2025 is expected to reduce that uncertainty by expressly recognising the tribunal’s power to dispose of unmeritorious claims efficiently. For parties involved in construction disputes, this may improve confidence in using London as a seat for expedited arbitration.

Next Steps: Drafting Smarter Dispute Resolution Clauses

Many standard construction contracts still contain dispute resolution clauses drafted before expedited arbitration procedures became widely used. Therefore, it may be beneficial to review your existing dispute resolution clauses, particularly within amended JCT, NEC, or FIDIC contracts.

Points worth considering include:

  • whether the contract expressly adopts ICC arbitration rules
  • whether the parties wish to opt into or preserve the ICC expedited procedure
  • whether the arbitration clause permits summary determination
  • how arbitration interacts with adjudication provisions
  • whether multi-party and multi-contract disputes are adequately addressed

The right drafting approach will depend on the project structure, governing law, jurisdictional risks, and the types of disputes most likely to arise.

Where a dispute is already developing, early strategic advice can also help you assess whether expedited arbitration is genuinely suitable, or whether a different route is available.

If you are dealing with an international construction dispute, reviewing arbitration clauses for a live project, or assessing whether expedited arbitration may help resolve a developing issue, Witan Solicitors is a solicitors’ firm serving UK projects through our construction law solicitors and arbitration services.

For advice on construction disputes and arbitration strategy, contact Witan Solicitors on 0300 303 2071.

How can we help you?

How would you prefer to be contacted?