Letters of Intent (LOI): The Legal Pitfalls of Starting Work Early

By: Qarrar Somji

Date: 07/03/2026

In construction, commercial pressure often drives parties to begin work before the formal building contract is finalised. A letter of intent construction arrangement is frequently used to bridge this gap, allowing mobilisation, procurement, or preliminary works to commence while negotiations continue.

However, what appears to be a pragmatic short-term solution can create significant legal uncertainty. Disputes frequently arise over whether a construction letter of intent is binding, what terms govern the relationship, and what happens if the full contract is never executed. Courts have repeatedly emphasised that starting work without a clearly agreed contractual framework can expose both employers and contractors to unexpected risks.

Below, we’ll examine what a letter of intent in construction is, why they are used, and the key legal pitfalls organisations must understand before relying on them.

Summary

  1. What a Letter of Intent Is (And Isn’t)
  2. Why Letters of Intent Are Used in Construction Projects
  3. Non-Binding Vs Binding: When an LOI Creates Legal Obligations
  4. The Uncertainty Trap: "Agreement to Agree" and Incomplete Terms
  5. Minimum Must-Haves: Scope, Programme, Price and Who Decides What
  6. Authority to Start: Early Works, Procurement and Site Access
  7. Payment Controls: Valuations, Caps and "Not-To-Exceed" Limits
  8. Time Controls: Validity Periods, Drop-Dead Dates and Rolling Extensions
  9. Risk Allocation: Insurance, Liability and Responsibility for Design and Defects
  10. Termination and Exit: What Happens if the Main Contract Never Lands
  11. Common Disputes And "Bear Traps" Highlighted By Case Law
  12. Best-Practice Drafting Checklist and How to Move to a Full Contract Fast
  13. Moving From Letter of Intent to Full Contract
  14. Why Letters Of Intent Require Careful Legal Management

What a Letter of Intent Is (And Isn’t)

A letter of intent (LOI) is typically a pre-contract document confirming that one party intends to enter into a construction contract with another. Its primary function is to permit limited works or preparatory activities while the parties finalise the detailed contractual terms. 

Crucially, an LOI is not automatically a contract. In many cases, it merely reflects a stated intention to reach agreement in the future. Whether it creates legally binding obligations depends on its wording, the surrounding negotiations, and the conduct of the parties. Courts will assess whether the essential elements of contract formation – including certainty of terms and intention to create legal relations – are present. 

This distinction is often misunderstood. Parties may assume that describing a document as a “letter of intent” prevents it from having contractual effect. In reality, its legal status depends on its substance rather than its label.

Why Letters of Intent Are Used in Construction Projects

Letters of intent are widely used in construction because projects are frequently driven by tight programmes, funding deadlines, or commercial imperatives. They allow early mobilisation while negotiations on risk allocation, pricing, or design responsibility continue. 

Typical scenarios include:

  • Urgent site preparation or enabling works to maintain programme momentum
  • Procurement of long-lead materials or specialist subcontract packages
  • Complex negotiations where key commercial terms remain unresolved
  • Funding or planning conditions requiring early activity

While commercially convenient, reliance on LOIs often reflects process risk rather than strategic necessity. Industry experience shows that they are sometimes issued simply because they have become routine practice, rather than because they are the most appropriate legal mechanism.

Non-Binding Vs Binding: When an LOI Creates Legal Obligations

One of the most contentious issues is whether a letter of intent gives rise to binding contractual obligations. Even where documents are marked “subject to contract”, a binding agreement may still arise if the parties’ words and conduct demonstrate an intention to be legally bound.

Courts will consider factors such as whether essential terms (e.g. scope, payment basis, programme) are sufficiently certain, whether work has commenced and payments have been made, and whether parties have acted in a manner consistent with a concluded agreement.

In practice, once substantial works have been performed, it can be difficult to argue that no contractual relationship exists at all. This can result in a “simple contract” being implied, but without the detailed protections normally found in standard-form construction contracts. 

The legal risk is therefore twofold: an LOI may be less protective than intended yet still create enforceable obligations.

The Uncertainty Trap: “Agreement to Agree” and Incomplete Terms

Letters of intent often fall into the category of an “agreement to agree” – a statement that the parties will finalise terms later. Such arrangements can create significant uncertainty where key commercial or risk allocation provisions remain unresolved.

Disputes frequently arise over issues such as:

  • Whether liability caps or limitation clauses apply
  • Which payment mechanism governs the early works
  • Whether standard contract conditions are incorporated
  • The extent of authorised works

Courts will not rewrite incomplete agreements or imply detailed contractual frameworks that the parties themselves failed to finalise. As a result, parties may find themselves bound by an arrangement that lacks clarity on critical matters such as insurance or design responsibility. For this reason, an LOI should always be approached on the assumption that the full contract may never be concluded.

Minimum Must-Haves: Scope, Programme, Price and Who Decides What

If a project must begin before the main contract is executed, the letter of intent should clearly define the essential commercial and operational framework for the authorised works.

At a minimum, this typically includes:

  • the scope of early works permitted
  • the programme or timeframe for those works
  • the agreed basis of payment
  • authority and decision-making mechanisms

The absence of clarity in any of these areas can lead to disputes over entitlement, delay, or variations. In practice, many conflicts arise because parties assume the main contract terms will eventually apply retrospectively. That assumption is not always legally or commercially safe.

An LOI should therefore be drafted as a self-contained interim contract, capable of governing the relationship if negotiations later fail.

Authority to Start: Early Works, Procurement and Site Access

A key function of a construction letter of intent is to authorise specific activities before full contractual commitment. This may include enabling works, design development, mobilisation, or procurement of long-lead items.

However, authorisation must be expressed with precision. Where the scope of early works is loosely defined, disputes can arise over whether certain activities were genuinely permitted or carried out at the contractor’s own risk.

Particular care is required in relation to:

  • procurement commitments entered into on the employer’s behalf
  • access rights to the site or existing structures
  • coordination with other contractors or consultants
  • ownership and responsibility for partially completed work

Without clear limits, the parties may find themselves operating under an informal project framework with uncertain allocation of risk.

Payment Controls: Valuations, Caps and “Not-To-Exceed” Limits

Payment arrangements under letters of intent are often one of the most contested issues. Employers may assume that a financial cap protects them from exposure, while contractors may believe they are entitled to payment for all authorised work.

In reality, disputes frequently arise where work exceeds the financial cap without formal extension, valuation mechanisms are unclear or incomplete, payment timing is not aligned with statutory adjudication regimes, or entitlement depends on later agreement of contract terms.

Courts have shown willingness to enforce caps contained in letters of intent, even where additional work has been undertaken. This can result in contractors carrying significant unrecovered costs if the authorised limit is exceeded without proper amendment. Clear, enforceable payment mechanisms are therefore essential.

Time Controls: Validity Periods, Drop-Dead Dates and Rolling Extensions

Letters of intent are intended to be temporary arrangements. In practice, however, they can remain in place far longer than originally envisaged.

Many disputes stem from expired LOIs under which work continues informally. This creates uncertainty over whether a new contract has arisen by conduct, or whether the original LOI still governs the relationship.

Common risk scenarios include:

  • expiry dates being overlooked while negotiations continue
  • repeated extensions creating ambiguity over contractual terms
  • programme delays arising from incomplete risk allocation
  • shifting project scope without formal contractual mechanisms

Time controls should therefore be treated as active project management tools, not merely administrative formalities.

Risk Allocation: Insurance, Liability and Responsibility for Design and Defects

One of the greatest dangers of relying on a letter of intent construction arrangement is that it often fails to address risk allocation in sufficient detail. Standard-form building contracts contain carefully structured provisions governing liability, insurance obligations, design responsibility, and indemnities. Letters of intent rarely replicate that level of precision.

This can create significant exposure for both employers and contractors. For example, uncertainty may arise as to whether:

  • the contractor’s professional indemnity or works insurance obligations have been triggered
  • design responsibility has formally transferred
  • limitations or exclusions of liability apply
  • responsibility for defects discovered later is governed by any agreed contractual framework

Where works proceed without these matters being clearly addressed, disputes frequently emerge long after the project has progressed. The parties may then find themselves attempting to reconstruct their intended risk allocation from fragmented correspondence or informal agreements.

In practical terms, the absence of defined risk allocation under an LOI can leave parties operating outside the protective structure of standard contractual provisions, with potentially serious financial consequences.

Termination and Exit: What Happens if the Main Contract Never Lands

A letter of intent should always anticipate the possibility that the anticipated construction contract will not ultimately be concluded. Yet this contingency is often insufficiently addressed in practice.

If negotiations break down after work has commenced, key issues can include:

  • entitlement to payment for completed or partially completed works
  • ownership of materials procured or fabricated off-site
  • demobilisation costs and programme disruption
  • liability for design development or temporary works

Without clear termination provisions, the parties may face uncertainty as to whether they can walk away, and on what terms. This can lead to protracted disputes about the legal basis of the relationship and the extent of recoverable costs.

In some cases, courts have found that the parties’ conduct resulted in the formation of a binding contract despite the absence of a signed agreement. In others, the absence of sufficiently agreed terms has left one party exposed to losses that would typically be managed through standard contractual mechanisms.

The key point is that an LOI should not be treated as a low-risk interim document. It must contain clear exit routes and financial consequences if the full contract is not finalised.

Common Disputes And “Bear Traps” Highlighted By Case Law

Judicial decisions repeatedly demonstrate that disputes arising from a construction letter of intent rarely concern whether work was carried out. Instead, they focus on what legal framework governs that work and what commercial protections apply. The following cases illustrate the most common pitfalls.

Starting Work Under a Letter of Intent

RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH & Co. KG

This 2010 Supreme Court decision remains a leading authority on whether a binding contract can arise despite the existence of a letter of intent marked “subject to contract”. The parties had commenced performance and continued negotiations on detailed terms.

The Court held that a legally binding agreement had been formed, emphasising that contractual intention is assessed objectively based on conduct and communications. The absence of a formally executed contract did not prevent contractual obligations from arising.

Key Takeaway: Starting work under a letter of intent can result in a binding contract being formed through conduct, even where the parties intended to formalise their agreement later.

Failing to Agree Critical Protections

Arcadis Consulting (UK) Ltd v AMEC (BSC) Ltd

This 2016 case concerned design services carried out in anticipation of a broader subcontract that was never finalised. Work had clearly been instructed and performed; however, a central issue was whether a proposed limitation of liability applied.

The court concluded that although a contractual relationship existed, there was insufficient certainty to incorporate the liability cap argued for by the consultant. The parties’ failure to reach agreement on key terms left significant commercial risk unresolved.

Key Takeaway: If critical protections such as liability caps are not clearly agreed, courts may decline to imply them, leaving parties exposed to greater risk than anticipated.

Enforcing Financial Caps

Diamond Build Ltd v Clapham Park Homes Ltd

The dangers of exceeding financial limits under a letter of intent were illustrated in this case from 2008. Here, the letter of intent contained a financial cap governing authorised expenditure. The contractor continued working beyond that limit while negotiations on the main contract remained ongoing.

The court enforced the cap, refusing to award payment for work exceeding the authorised amount. This outcome underlines the importance of actively managing financial limits and ensuring extensions are formally documented.

Key Takeaway: Financial caps in letters of intent can be strictly enforced, even where additional work has been carried out in good faith.

Assessing Payment without Contract

British Steel Corporation v Cleveland Bridge & Engineering Co Ltd

Earlier authority also demonstrates the challenges of determining entitlement to payment where negotiations fail and the consequences of not concluding a formal contract. Work proceeded under preliminary arrangements, but no comprehensive agreement was finalised.

The court determined that payment entitlement should be assessed on a restitutionary basis rather than under contractual terms. This created uncertainty over valuation and commercial risk allocation.

Key Takeaway: Where no contract is formed, payment may be assessed on a quantum meruit basis, creating unpredictability in project cost recovery.

Using LOIs to Govern Long Term

Spartafield Ltd v Penten Group Ltd

This dispute arose after prolonged reliance on a letter of intent while negotiations on a formal contract continued. The court was required to determine whether the parties’ conduct had effectively resulted in a replacement contract despite the absence of signature.

The case highlights how extended use of interim arrangements can blur the legal framework governing the project, leading to complex and costly litigation.

Key Takeaway: Allowing letters of intent to govern works for extended periods increases the risk of disputes over contractual formation and applicable terms.

Best-Practice Drafting Checklist and How to Move to a Full Contract Fast

A well-drafted letter of intent in construction should not simply enable early mobilisation. It must also provide a clear interim legal framework capable of governing the parties’ relationship if negotiations on the full contract stall or fail.

In practice, many disputes arise not because a letter of intent was used, but because it lacked sufficient precision. The following areas typically require particular attention.

Define the Authorised Scope with Precision

The LOI should clearly state what work is permitted and what remains conditional upon execution of the main contract. Ambiguity in this area can lead to disputes over whether activities were authorised or undertaken at risk.

Careful drafting can help avoid situations where parties later disagree on whether enabling works, design development, or procurement commitments fell within the intended scope.

Establish a Clear Payment Mechanism

Interim arrangements often overlook the detailed valuation and payment provisions normally found in construction contracts. This can create uncertainty around entitlement, timing, and dispute resolution.

A robust LOI should therefore specify the basis of payment, including valuation procedures and any financial caps. Without this clarity, parties may face significant uncertainty if the project does not proceed as anticipated.

Address Programme and Duration Controls

Letters of intent are intended to be temporary measures, yet projects frequently continue under them for longer than originally envisaged.

Defined validity periods, extension mechanisms, and “drop-dead” dates help ensure that the LOI does not become a de facto long-term contractual framework. Active management of these provisions is essential to maintaining commercial certainty.

Clarify Risk Allocation and Insurance

Standard construction contracts allocate risk through detailed provisions on liability, indemnities, and insurance. Letters of intent often omit or simplify these issues, which can leave critical exposures unresolved.

This is particularly significant where early works involve design responsibility, structural intervention, or procurement of major materials. In such circumstances, the absence of clear risk allocation can have lasting financial consequences.

Include Clear Termination and Transition Provisions

An LOI should address what happens if the anticipated construction contract is never concluded. This includes entitlement to payment, ownership of materials, and obligations upon demobilisation.

Equally important is the transition mechanism to the full contract. The document should make clear how and when the LOI’s provisions will be superseded once formal terms are agreed.

Moving From Letter of Intent to Full Contract

While letters of intent can provide commercial flexibility, they should not replace the discipline of concluding a comprehensive construction contract. Prolonged reliance on interim arrangements increases legal uncertainty and can weaken the parties’ negotiating positions.

In practice, the most effective approach is to treat the LOI as a strictly time-limited tool while prioritising agreement on the full contractual framework. Ensuring that the key commercial and risk allocation issues are resolved at an early stage can significantly reduce the likelihood of costly disputes later in the project lifecycle.

Letters of intent are a familiar feature of construction procurement, often used to maintain programme momentum while contractual negotiations continue. However, as the case law demonstrates, they can create significant legal and commercial uncertainty if relied upon without careful drafting and active management.

Whether disputes arise over contractual formation, payment entitlement, liability allocation, or termination rights, the consequences can be costly and disruptive. A construction letter of intent should therefore be approached as a legally significant interim agreement rather than an informal administrative step. Ensuring that it provides a clear and enforceable framework for early works is essential to protecting both commercial interests and project delivery.

If you are considering issuing or accepting a letter of intent construction arrangement, early legal advice can help prevent avoidable risk. Witan’s construction law specialists regularly advise employers, contractors, and consultants on drafting, reviewing, and negotiating letters of intent, as well as resolving disputes arising from their use. For practical, commercially focused guidance tailored to your project, contact our construction team today.

How can we help you?

How would you prefer to be contacted?