Public sector framework agreements are part of the procurement process, providing a structured way for contracting authorities to procure construction works and services without conducting a full procurement exercise for every project. They are widely used across public infrastructure, building maintenance and construction programmes, offering opportunities for contractors to secure work over an extended period.

However, securing a place on a framework does not necessarily guarantee future contracts. Individual projects must still be awarded through the appropriate call-off procedures, and both contractors and contracting authorities must comply with the relevant procurement legislation and contractual requirements.

With the Procurement Act 2023 introducing significant changes to public procurement, understanding these obligations is particularly important. This guide explains the legal framework governing public sector construction frameworks, how call-off procedures operate and the commercial and legal risks to consider.

Public sector construction framework agreements are governed primarily by the Procurement Act 2023, which came into force on 24 February 2025. The Act establishes the rules for awarding public contracts in England, Wales and Northern Ireland, although separate procurement legislation generally applies in Scotland.

The Procurement Act 2023

Sections 45–49 of the Act govern framework arrangements, including their establishment, duration and the award of individual contracts. Under section 45, frameworks must identify the works or services covered, pricing arrangements, participating authorities and procedures for awarding contracts.

Most frameworks are limited to four years, although utilities and defence frameworks may run for eight years. Longer periods are permitted where justified by the nature of the works or services, with reasons documented in the procurement notice.

The Act also introduces open frameworks, allowing suppliers to compete for places at specified intervals. These arrangements can operate for up to eight years, subject to statutory conditions, offering greater flexibility than conventional frameworks.

Existing Frameworks and Transitional Arrangements

Not all public sector framework agreements operate under the new legislation. Frameworks established under the Public Contracts Regulations 2015 before 24 February 2025 generally remain governed by those regulations until they expire. Individual contracts awarded through these frameworks also remain subject to the previous rules.

This distinction matters when procuring construction works. Contracting authorities must follow the procedures applicable to the particular framework, rather than assuming the Procurement Act 2023 governs every new call-off.

Before entering into a framework arrangement, contractors and authorities should establish which legislation applies and review the relevant procurement documentation. This helps identify the appropriate award procedures and reduces the risk of non-compliance.

Crown Commercial Service (CCS) Framework Agreements

The Crown Commercial Service is the largest public procurement organisation in the UK. It provides framework agreements for public sector procurement of goods, services and works from pre-approved suppliers.

CCS frameworks cover a wide range of requirements, including construction, facilities management and professional services.

For construction projects, these arrangements simplify procurement by allowing contracting authorities to select suppliers through established award procedures, rather than conducting a separate procurement exercise for every contract.

How CCS Frameworks Work

Suppliers must first compete for a place on a CCS framework, demonstrating that they meet the relevant selection and award criteria. Once appointed, they become eligible to compete for, or receive, individual contracts through the framework’s permitted call-off procedures.

However, appointment to a CCS framework does not guarantee work. Contracting authorities may choose between eligible suppliers, and the volume of available opportunities will depend on demand throughout the framework’s duration.

Contractors should therefore consider the commercial implications before committing resources to a framework application. This includes reviewing the framework’s scope, pricing arrangements, contractual obligations and anticipated opportunities.

Equally, contracting authorities must ensure that their proposed works fall within the framework’s scope and that they follow the prescribed call-off procedures.

Man writing in an open ledger at a counter by a window to check central purchasing body framework terms

Central Purchasing Bodies: What to Watch for

Central purchasing bodies (CPBs) establish framework agreements that other contracting authorities can use to procure construction works and services. While this can reduce procurement costs and administrative burdens, using a third-party framework introduces additional legal and commercial considerations.

Before awarding a contract, authorities must confirm that they are entitled to use the framework and that the proposed works fall within its scope. A framework cannot automatically be used by any public sector organisation simply because it offers suitable services.

Responsibility for procurement compliance also requires careful consideration. Although a CPB may establish and manage the framework, contracting authorities remain responsible for the procedures they conduct themselves, including individual call-off awards.

Commercial Risks and Transparency

CPBs may charge management fees or operate commercial arrangements with framework suppliers. These arrangements warrant scrutiny, particularly where fees affect project costs or create potential conflicts between the interests of suppliers and purchasing authorities.

Contractors and authorities should therefore examine:

  • Framework eligibility: Whether the purchasing authority and proposed works are covered.
  • Fees and charges: How management fees are calculated and who bears the costs.
  • Contractual responsibilities: Which organisation is responsible for procurement decisions and subsequent contractual obligations.

For example, if a local authority awards construction works through a framework that does not cover the proposed project, the award may be vulnerable to a procurement challenge.

Once a framework agreement is established, contracting authorities can award individual contracts through its prescribed call-off procedures. However, the rules differ depending on whether the framework was established under the Procurement Act 2023 or the Public Contracts Regulations 2015.

Competitive Selection and Direct Awards

Under section 45 of the Procurement Act 2023, competitive selection is the default. A framework may only provide for future contracts to be awarded after a competitive selection process, in which eligible framework suppliers submit bids. Under section 46, any conditions of participation must be proportionate. The authority may assess bids only against the award criteria used to award the framework, although it can refine those criteria for the call-off.

An authority can award a contract without competition in only two cases. The first is a framework with a single supplier. The second is a framework that sets out both the core terms of the contract and an objective mechanism for selecting the supplier.

The competitive selection default in section 45 and the rules in section 46 do not apply to a framework that is a light touch contract, meaning a contract for services of a type set out in regulations under Section 9(2) of the Act.

For older frameworks governed by Regulation 33 of the Public Contracts Regulations 2015, different requirements apply to direct awards and further competitions.

In either case, authorities must follow the applicable framework rules. Departing from the prescribed procedures could expose the award to a legal challenge.

Contractual Scope and Changes to Terms

Call-off contracts must remain within the scope of the original framework. Authorities cannot use an existing framework to procure substantially different works or introduce changes that fall outside its permitted terms.

For example, a framework established for routine building maintenance may not permit the award of a major construction project simply because the appointed contractor has the necessary capabilities.

Similarly, proposed changes to pricing, specifications or contractual obligations must be assessed against the framework terms and applicable procurement legislation.

Scales weighing a banded document against stacked ledgers while a man works at a laptop, showing a call-off gone wrong

What Happens When a Call-Off Goes Wrong?

An incorrectly awarded call-off contract may be challenged by an affected supplier. Depending on the circumstances, remedies can include damages, suspension of the award process or orders affecting the contract itself.

The risks extend beyond legal proceedings. A procurement dispute can delay construction programmes, increase costs and damage commercial relationships. Contracting authorities should therefore maintain clear records explaining how suppliers were selected and why the proposed works fall within the framework.

For contractors, reviewing the call-off documentation before accepting an award can help identify inconsistencies, unexpected obligations or potential disputes before work begins. Where call-off contracts use standard forms, our guide to JCT contracts explains how those forms work.

Private Sector Framework Models

Framework agreements are also widely used in the private sector, particularly by developers, commercial property owners and organisations managing ongoing construction or maintenance programmes.

Unlike public sector frameworks, private sector arrangements are generally not subject to statutory public procurement procedures. This provides greater flexibility in selecting suppliers, negotiating terms and awarding individual contracts.

Private sector frameworks may operate through different commercial models, including agency models and neutral vendor models. In an agency model, an intermediary manages procurement arrangements on behalf of a client, with contracts typically formed directly between the client and supplier.

In a neutral vendor model, an independent intermediary manages a network of suppliers, coordinating procurement and contract delivery without directly providing the underlying works or services.

Although these arrangements offer flexibility, clear contractual terms remain essential. Parties should establish responsibility for supplier selection, payment, performance and dispute resolution. Without these safeguards, disagreements over contractual obligations or the intermediary’s role can create significant commercial risks.

How Witan Can Help

Public sector framework agreements offer valuable opportunities for construction businesses, but unclear contractual terms and disputes over individual call-offs can create significant commercial risks.

At Witan Solicitors, our construction law specialists can help you understand your contractual obligations, review framework and call-off agreements, and identify potential risks before they develop into disputes.

Whether you are concerned about payment provisions, contractual liability or a disagreement arising during project delivery, we can provide practical legal advice tailored to your circumstances. Simply contact our construction law team or call 0300 303 2071.